Infrastructure · Road & drainage / Aug–Oct 2026

Nyang Nyang Infrastructure

Road formation and drainage delivery, with excavation, precast U-ditch installation, pit construction and survey / utility coordination.

Excavator working along the drainage trench at Nyang Nyang

Nyang Nyang Infrastructure · Site photograph from the drainage construction works.

My role
Project Manager
Company
AYA Development Advisor
Location
Nyang Nyang, Bali
Involvement
Aug–Oct 2026

My responsibilities

  • Coordinated site execution across road preparation, drainage excavation, precast U-ditch installation and pit works.
  • Monitored quantities and progress against the Phase 1 work scope and communicated daily / weekly site status.
  • Coordinated survey validation using Emlid equipment and reference points from the surveyor’s drawings.
  • Followed up contractor activities, site access, plant and material requirements, and utility coordination including PLN pole relocation.
  • Identified work dependencies and next actions for road and drainage activities.

Progress snapshot · 12–18 October 2026

415 mOverall internal road development scope
230 mPhase 1 road length
183 mU-ditch installed in the October progress update

At the latest recorded update, 8 of 13 drainage pits had been completed. These are progress figures, not final completion claims.

Delivery evidence & status

Photographs personally taken during excavation, drainage alignment and precast U-ditch installation. The October 2026 progress snapshot records work completed during my involvement; remaining road and drainage activities continued beyond the photographed stages.