Infrastructure · Road & drainage / Aug–Oct 2026
Nyang Nyang Infrastructure
Road formation and drainage delivery, with excavation, precast U-ditch installation, pit construction and survey / utility coordination.

Nyang Nyang Infrastructure · Site photograph from the drainage construction works.
- My role
- Project Manager
- Company
- AYA Development Advisor
- Location
- Nyang Nyang, Bali
- Involvement
- Aug–Oct 2026
My responsibilities
- Coordinated site execution across road preparation, drainage excavation, precast U-ditch installation and pit works.
- Monitored quantities and progress against the Phase 1 work scope and communicated daily / weekly site status.
- Coordinated survey validation using Emlid equipment and reference points from the surveyor’s drawings.
- Followed up contractor activities, site access, plant and material requirements, and utility coordination including PLN pole relocation.
- Identified work dependencies and next actions for road and drainage activities.
Progress snapshot · 12–18 October 2026
415 mOverall internal road development scope
230 mPhase 1 road length
183 mU-ditch installed in the October progress update
At the latest recorded update, 8 of 13 drainage pits had been completed. These are progress figures, not final completion claims.
Delivery evidence & status
Photographs personally taken during excavation, drainage alignment and precast U-ditch installation. The October 2026 progress snapshot records work completed during my involvement; remaining road and drainage activities continued beyond the photographed stages.





For further project details or a discussion about my experience, get in touch.